Topic Sponsor
2009 - 2014 Ford F150 General discussion on 2009 - 2014 Ford F150 truck.
Sponsored by:
Sponsored by:

Lead time?

Thread Tools
 
Search this Thread
 
Old Feb 4, 2013 | 08:55 AM
  #31  
SlowFocus's Avatar
Senior Member
 
Joined: Dec 2012
Posts: 351
Likes: 43
From: British Columbia
Default

Originally Posted by LionAround
Update: Ordered on 1/7/13, dealer got confirmation on 1/11/13, received my VIN 2 weeks after being ordered with build date of 1/29/13. Dealer received truck on 1/31/13 and I got it same day. Truck was built in Dearborn and I live in northern OH 1 hour away. I love this thing. It the shop now changing out those crappy Wrangler SR-A's for some SilentArmor 275/70 - 18's.
That's fast!!!

My dealer just gave us a build date of Feb 11, and said that it would take 4 days to go through the plant. Is that possible?
Reply
Old Feb 4, 2013 | 09:29 AM
  #32  
av8torken's Avatar
Senior Member
 
Joined: Jan 2013
Posts: 647
Likes: 107
Default

Originally Posted by my2013Lariat
Guess it is a good thing I ordered the Lariat then. Good luck. Hope it comes through soon.
Wouldn't have mattered if I ordered a Lariat either.
Reply
Old Feb 4, 2013 | 10:59 AM
  #33  
Zixxer10r's Avatar
2013 King Ranch EB GemGrn
 
Joined: Dec 2012
Posts: 482
Likes: 80
Default

Hey bud, I took delivery of my KR on Thursday. From order point to delivery it was a total of 7 weeks.
Reply
Old Feb 4, 2013 | 11:18 AM
  #34  
av8torken's Avatar
Senior Member
 
Joined: Jan 2013
Posts: 647
Likes: 107
Default

Originally Posted by Zixxer10r
Hey bud, I took delivery of my KR on Thursday. From order point to delivery it was a total of 7 weeks.
Who are you talking to?
Reply
Old Feb 4, 2013 | 11:21 AM
  #35  
Zixxer10r's Avatar
2013 King Ranch EB GemGrn
 
Joined: Dec 2012
Posts: 482
Likes: 80
Default

Originally Posted by av8torken
Who are you talking to?
You. I told you I would update you when I actually took delivery of the truck. 7 weeks. Nearly to the day.

Here's hoping you get yours sooner rather than later.
Reply
Old Feb 4, 2013 | 11:29 AM
  #36  
av8torken's Avatar
Senior Member
 
Joined: Jan 2013
Posts: 647
Likes: 107
Default

Originally Posted by Zixxer10r
You. I told you I would update you when I actually took delivery of the truck. 7 weeks. Nearly to the day.

Here's hoping you get yours sooner rather than later.
Oh yeah, it's been awhile, and I doubt anything is going to happen soon.
Reply
Old Feb 4, 2013 | 12:25 PM
  #37  
Madorski's Avatar
See? It works in monkeys!
 
Joined: Jan 2013
Posts: 348
Likes: 41
From: Whitehorse, Yukon
Default

Not bad... I got my VIN last Thursday - two months to the day to get my VIN - scheduled for production on February 11th, and a delivery of March 4th.


Body Code: W1E
Vehicle Line: F-150
Primary: In Order Processing
Secondary: Scheduled to day (2013-02-11)
Vehicle Location: Ford Kansas City Assembly, MO
Status Date / Time: Jan-26-2013
ETA: *Mar-04-2013

Rail is the most economical, but not the fastest. If there's a load going to Central or Eastern Canada, my truck may sit in Kansas City for weeks before a load is put together to go West, or it could sit on a train going from hub to hub. I've seen trucks zig-zag across North America for weeks before being offloaded...
Reply
Old Feb 4, 2013 | 04:36 PM
  #38  
LionAround's Avatar
Junior Member
 
Joined: Jan 2013
Posts: 24
Likes: 3
Default

4 days seems like a bit much. That thing is built in about 1-1.5 shifts (if I remember). There are only 2 things I know of that could cause it to take 4 days to get out of the plant. 1) A yard hold for quality issues, and/or 2) your truck gets picked for an audit so it gets scheduled it to be taken out and put 40-70 miles on while they check NVH, fit/finish, power train, etc.
Reply
Old Feb 4, 2013 | 10:16 PM
  #39  
av8torken's Avatar
Senior Member
 
Joined: Jan 2013
Posts: 647
Likes: 107
Default

Originally Posted by Madorski
Not bad... I got my VIN last Thursday - two months to the day to get my VIN - scheduled for production on February 11th, and a delivery of March 4th.


Body Code: W1E
Vehicle Line: F-150
Primary: In Order Processing
Secondary: Scheduled to day (2013-02-11)
Vehicle Location: Ford Kansas City Assembly, MO
Status Date / Time: Jan-26-2013
ETA: *Mar-04-2013

Rail is the most economical, but not the fastest. If there's a load going to Central or Eastern Canada, my truck may sit in Kansas City for weeks before a load is put together to go West, or it could sit on a train going from hub to hub. I've seen trucks zig-zag across North America for weeks before being offloaded...
Is your dealer a small dealer too? If it took you 8 weeks, then there is still hope..
Reply
Old Feb 4, 2013 | 10:37 PM
  #40  
SlowFocus's Avatar
Senior Member
 
Joined: Dec 2012
Posts: 351
Likes: 43
From: British Columbia
Default

Originally Posted by Madorski
scheduled for production on February 11th, and a delivery of March 4th.
I've been given the exact same build date and delivery ETA (I'm in the Vancouver area). Can't wait!
Reply



All times are GMT -4. The time now is 07:30 PM.